Meaning
Lead time is the calendar from approved drawings to delivered profile, made up of die making, sample approval, production and finishing. Published figures for each block come from suppliers’ own pages. They describe plants that sell in volume, so a small run reads them as lower bounds.Die Weeks
Both the AEC white paper and one extruder’s data sheet allow 2 to 3 weeks to make a new aluminum die. Another extruder states 2 to 4 weeks and more for complex, large or intricate shapes. Hydro puts hollow dies at the slow end, since their two-part tools need more design and machining. Samples are then approved before production is booked.Read More
Production Weeks
Production of a standard shape, mill finish or clear anodized, takes 3 to 4 weeks at one plant. Adding powder coat stretches that plant’s time to about 6 weeks. Another notes that production time depends mostly on where the order falls in its schedule. Fabrication adds days or weeks depending on complexity and batch size.Plastic Tooling
The sources opened for these resources print no lead time for plastic profile tooling. They give no typical number of die trials either. A buyer therefore asks for the die date in writing, counted from approved drawings. The same request covers how many trials are planned and whether each is its own line booking.Reading the Figures
Some published lead times include the finish and some leave it out. Two quotes are compared only after that is settled. On a run of a few tonnes, the timing of die nitriding is also asked, since it can add to the schedule. A date confirmed after drawings are sent outweighs any figure on a public page.